Flow Under Control: Critical Overpumping at Fazakerley STW
Project Overview
Pump Supplies Ltd was appointed to deliver a fully engineered emergency overpumping solution at Fazakerley Sewage Treatment Works following the catastrophic failure of a large-diameter valve within the inlet works.
The project required the entire incoming flow to be temporarily diverted so the inlet works could be drained and the failed valve safely replaced, all while maintaining uninterrupted treatment operations.
With sustained process flows of over 820 litres per second, the project required a substantial temporary pumping system, standby capacity, power generation, extensive pipework and remote monitoring. Pump Supplies mobilised and implemented the system within just 10 days, with the overall project running for eight weeks.
The Challenge
The valve failure created an immediate operational and environmental risk. Without a functioning valve, the treatment works could no longer effectively regulate incoming flows.
Taking the inlet works offline was not straightforward. Pump Supplies needed to create a temporary system capable of handling the site’s entire incoming flow while allowing the affected area to be drained and repaired. The system needed to continuously manage more than 820 litres per second, with very little time available for design and mobilisation.
There was another significant complication: storm flows.
Under normal operation, additional flows during storm conditions could be diverted to dedicated storm tanks and gradually returned to treatment once wastewater volumes reduced. With the inlet works offline, there was a risk that rapidly increasing storm flows could overload downstream processes.
The temporary installation also involved numerous additional pumps and associated equipment, meaning the electrical load had to be carefully balanced against the available supply.
Above all, the system had to be designed, delivered, installed and commissioned safely without disrupting the live treatment process.
The Solution
Pump Supplies mobilised quickly, designing and implementing a complete overpumping system within just 10 days.
The solution used three 180kW Flygt N pumps and approximately 1,000 metres of ductile iron pipework to bypass the affected inlet works and maintain the main flow through the treatment process. Each pump was fitted with VFD control, telemetry and remote monitoring, providing continuous visibility and allowing for a rapid response to potential issues.
Additional submersible and diesel pumps were installed to provide the extra capacity required during storm conditions, while standby power and pumping capacity added further resilience to the temporary system.
With the treatment works remaining live throughout, detailed site surveys, lifting plans, environmental controls and carefully engineered pipework routes ensured the system could be installed and commissioned safely and with minimal disruption to ongoing operations.
END RESULT
The temporary overpumping system allowed the failed valve to be repaired while maintaining treatment operations throughout the project.
Despite the urgency, scale and sensitivity of the work, Pump Supplies delivered the installation safely and efficiently, giving the client the time required to carry out a robust valve repair rather than being forced into the quickest possible solution.
Importantly, the benefits extended beyond resolving the immediate failure. According to the case study, the project helped improve the site’s resilience, monitoring capability and operational confidence, while also preventing potential pollution during the incident and strengthening procedures intended to reduce the likelihood of future environmental non-compliance.
The result was a complex, high-capacity temporary pumping operation delivered without disruption to treatment, demonstrating Pump Supplies’ ability to respond rapidly when reliability, engineering expertise and operational resilience are critical.
“Pump Supplies mobilised quickly and delivered a complex overpumping solution with exceptional professionalism and safety. The quality of the installation and seamless operation impressed both ourselves and United Utilities. A reliable partner we look forward to working with again.”
Kevin Rose, Senior Mechanical Operations Engineer, Avove Ltd